3750 kVA Pad-Mount

3750 kVA Pad-Mount Transformers For Sale

3750 kVA sits near the top of the typical three-phase pad-mount range. These units serve heavy industrial loads, data center capacity blocks, and large solar, storage, and EV charging interconnections.

New three-phase pad-mount units are commonly quoted at roughly 34–65 weeks from major manufacturers in 2026 (see current lead times). Used and surplus units are the fastest path to energizing on schedule.

We don’t have a 3750 kVA unit listed right now. Send us your voltage and timeline and we’ll check our sourcing network, or sign up below to be emailed when one is listed.

Request a 3750 kVA Unit

Inventory turns over. Get an email when new units in your size are listed.

Choosing a 3750 kVA pad-mount transformer

Two 3750 kVA units can be very different transformers. Before you compare prices or availability, confirm these specs match your project:

Full-load current at 3750 kVA

Secondary voltageFull-load current per phase
480Y/277V4,511 A
208Y/120V10,409 A

Calculated as kVA × 1000 ÷ (1.732 × secondary voltage).

New vs. used: what it means for your schedule

New three-phase pad-mount units are commonly quoted at roughly 34–65 weeks from major manufacturers in 2026, and custom specs often take longer. A used or surplus unit is already built, so the wait is mostly about verification, testing, and freight. Before buying any used unit, review its nameplate, oil test results, and electrical test records. See current lead times and sources or read what to check before buying used.

3750 kVA pad-mount FAQ

What is the full-load current of a 3750 kVA transformer at 480V?

A 3750 kVA three-phase transformer with a 480Y/277V secondary has a full-load current of about 4,511 amps per phase (kVA × 1000 ÷ (1.732 × 480)). At 208Y/120V the same rating would be about 10,409 amps. Your electrical engineer sizes the service equipment and protection from these values.

Can a 3750 kVA pad-mount with a 480Y/277V secondary be used for 208V?

Not by itself. The tap changer on a pad-mount adjusts the primary (high-voltage) side, not the secondary. A 480Y/277V unit delivers 480Y/277V. If your building needs 208Y/120V, you need a unit built with that secondary, or step-down transformers downstream.

How long does a new 3750 kVA pad-mount transformer take to get?

New three-phase pad-mount units are commonly quoted at roughly 34–65 weeks from major manufacturers in 2026, with custom specs often longer. A used or surplus unit that's already built can be available much sooner. See our transformer lead times page for sources.

Other Sizes

1500 kVA · 2000 kVA · 2500 kVA · 3000 kVA